Oracle Forms Upgrade – Reduction of estimated Effort
Posted on July 18, 2012 by Patrick
Last week I started a Upgrade Project for around 250 Forms and Libraries. The original Estimate was 23 Days with our Tool PITSS.CON.
Before I started the Upgrade, I did a unused Code analyze and that droped around 10% Lines of Code. Even more amazing was, that the Upgrade analyze now reduced the Effort by 25%. The cleaning of the Code just took me one day but I saved over 5 days.
I think it is worth for any Modernisation Project to think about Re-Engineering.
For me this a mind blowing Project.
viaPatrick's Oracle Modernization Experience | Oracle Forms Modernization and Upgrade, Oracle Forms2ADF Migration, Oracle Forms2APEX Migration.
Gefällt mir Wird geladen …
Ähnliche Beiträge
Über Jan-Peter
Jetzt sind es schon fast wieder 10 Jahre her und immer noch ist Migrationen Forms und Reports angesagt. Als ich 2015 damit begonnen habe, konnte ich mir nicht wirklich vorstellen, das es so lange anhält, aber es wird immer mehr und es ist immer wieder verwunderlich wer heute noch alles Oracle Forms in den Versionen 4x und 6i nutzt. Es überrascht mich doch immer wieder. Habe mich auf den Bereich komplett konzentriert und finde es immer wieder spannend was dort so an migrationen getätigt werden.